

PHASE 2
The design process for the replacement and refurbishment of the school on the main site is progressing. The plan is to keep and refurbish the Victorian building, which is the red sandstone building on Craighall Road. We would then demolish all the other buildings and construct new facilities which will adjoin the Victorian building.
Key milestones
• Ongoing staff engagement – June 2022 – Complete
• Community Council meeting – 13 June 2022 – Complete
• RIBA (Royal Institute of British Architects) Stage 2 Concept Design report – end of July 2022 – Complete
• Further school community engagement – August/Sept 2022 onwards – Complete
• Submission of planning application – winter 2022/23 – Complete
• Beginning of mobilisation phases – summer 2023 – Complete
• Construction of Learning Village begins – February 2024 – Complete
• Move to Learning Village – October 2024 – Complete
• Demolition of blocks B & C begins – spring/summer 2025 – Complete
• Target date for completion of all construction – 2028

CONSTRUCTION & NEWSLETTERS
The current plan for the construction programme is that it will run for five school sessions from 2023 to 2028. The exact construction phasing is well developed and includes the following:
We continue to keep both Trinity Academy families and our wider Learning Community families updated through the Newsletter. Links to these are below.